EXperience

Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2016 Dubai Petroleum / Technip Rashid C Project 42” 5.50 Flooding, Cleaning, Gauging and Hydrotesting Dubai
2016 McDermott Middle East / ADMA OPCO EPC for the facilities of 4 Gas Injectors (4GI) , Facilities for 32 New Oil Producers and Modifications on GIP Projects
Phase 2
2 x 12” 11.00/3.40 Caliper pigging, intelligent pigging, dewatering, drying and nitrogen purging Abu Dhabi
2016 PTTEP/COOEC Zawatika Development Project Ph 1B 18”/14”/18”/18” 30/18/18/5 Flooding, Cleaning, Guaging, Hydrotesting, Riser Testing, Final Leak Testing Myanmar
2016 Saudi Aramco / L & T Arabia Midyan Gas Power Plant Project - - Rental of Filling Pumps Saudi Arabia
2016 Dutco McConnel Dowell / DUSUP DUSUP – Margham Capacity Increase Project Pipe Sections Various Dia Hydrotest and Flushing of Pipe Spool Work Dubai
2016 NDT Global ADCO Habshan - - Supply of technicians on rental basis Abu Dhabi
2016 Hwachon Plant Construction Company / Barakah Nuclear Power Plant (BNPP) BNPP CP –P1 (II) Project Acid Cleaning – 40.37 m3
Oil Flushing – 41.01 m3
- Acid Cleaning & Oil Flushing Work for process piping Abu Dhabi
2016 ADCO / CCC Qusawira Project - - Supply of diesel pumping spread and Nitrogen Pumping Spread for Intelligent Pigging works Abu Dhabi
2016 Saipem Saudi – MRJN & Zulu Pipeline Project - - Dewatering of Infield Pipeline with Nitrogen Gas Saudi Arabia
2016 Audex Fujairah Project - - Vapour Blasting Equipment Rental Fujairah
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2015 ACS Offshore SPRL / Swiber Offshore Vega Pleyade Offshore Project 24” / 4” 77 / 77 Flooding, Cleaning, Gauging, Hydrotesting and Leak Testing Argentina
2015 NPCC / ZADCO - - - Supply of filling pumps and technicians Abu Dhabi
2015 Technip/Dubai Petroleum EPC for Installation of offshore pipelines – Rashid C Project 18” / 10”
12” / 8”
10” / 6”
30”
25.5 / 0.3
29.9 / 0.3
31.2 /0.3
5.23
Flooding, Cleaning/Gauging, Hydrotesting and Dewatering Dubai
2015 NSRP, JGCS/SKI, HHI Nighi Son Refinery Project, SBP 48" 70 Flooding, Cleaning, Gauging, Hydrotesting, SBM Leak Test, Caliper EGP Survey, Dewatering, Nitrogen Purging Vietnam
2015 Al Wasimi Holdings / Saudi Aramco/ Shaibah Interconnecting Pipelines 36” / 30” 27.0/27.0 Cleaning, Gauging, Hydrotesting, Dewatering, Drying, Nitrogen Purging, Caliper Pigging and Intelligent Pigging Saudi Arabia
2015 Supreme Offshore Private Limited/BG Exploration India/ BG Pipeline Project, India 10” 8.0 Flooding, Cleaning, Hydrotesting and Dewatering India
2015 Gas Authority of India Limited (GAIL) GAIL KG Basin Pipeline Project 8”, 12”, 14”, 16” & 18” Approx. 400 Inertization, Hydrotesting, Dewatering, Swabbing, Vacuum Drying and Commissioning India
2015 Gas Authority of India Limited (GAIL) GAIL KG Basin Pipeline Project 8”, 12”, 14”, 16” & 18” Approx. 400 Online Pigging India
2015 Rosen Gasco Habshan Inspection Works - - Supply of 4” Temporary Launcher and Receiver Dubai
2015 Quest Integrity Group / Dubai Petroleum 16” FA – FB Project 16” 7.70 Dewatering and Nitrogen Purging Dubai
2015 Lin Scan ADCO – UT Survey at NEB Field - - Supply of pumping spread and manpower on rental basis for UT Survey Abu Dhabi
2015 Hyundai Engineering Group III Base Oil Production Facilities in Takreer Ruwais 4”, 6”, 8” & 18” Pipe Sections Various Lengths Water Flushing, Cleaning Pigging of Interconnecting, Jetty and Process Piping
Water flushing cleaning works
Abu Dhabi
2015 Dubai Petroleum EPC for Installation of offshore pipelines – Rashid C Project - - Hire of Bolt Torqueing Equipment and Technicians Dubai
2015 McDermott Middle East / ADMA OPCO EPC for the facilities of 4 Gas Injectors (4GI) , Facilities for 32 New Oil Producers and Modifications on GIP Projects
Phase 1
2 x 12” 11.00/3.40 Flushing, flooding, cleaning, gauging, hydrotesting, Abu Dhabi
2015 ADCO/Galfar Engineering EPC For New WAG Wells & Conversion of Existing Gas Injector Wells at WAG Wells at Sahil
ADCO Contract No:
15646.01/EC 10875
4”/6” From 0.2 Km to 7.00 Cleaning, Gauging, Hydrotesting, Dewatering, Drying & Nitrogen Purging Works Abu Dhabi,
Sahil Fields
2015 Gulf Eco Friendly Services LLC Gas Pipeline Project 12” 2.70 Cleaning, Gauging, Hydrotesting, Dewatering, Swabbing, Drying and Nitrogen Purging Sharjah
2015 Alsa Engineering ADCO Project - - Rental of Compressor Abu Dhabi
2015 Lin Scan ADMA OPCO Project - - Supply of Flooding Spread on rental basis Abu Dhabi
2015 Rosen / Total ABK Total ABK Pipelines De-oiling and Baseline Inspection Project 16”/ 8”/10” 2.16 / 2.06 / 0.75 Assistance in providing manpower and equipment spread for de-oiling, gauging, caliper and intelligent pigging Abu Dhabi
2015 DUSUP / Dutco McConnel Dowell DUSUP Valve Testing Project 2” to 14” Dia - Testing of Ball and Globe Valves Dubai
2015 JGCS/PTSC Nighi Son Refinery Project, SBP 48" 3 Gauging & Cleaning, Hydrotesting Vietnam
2015 Krisenergy/Equatorial Wassana Field Development Project 6 / 4 2.5 / 2.5 Free Flooding, Pre-Testing, Post Intallation Leak Testing of Flexible Hoses Thailand
2015 DUSUP / Dutco McConnel Dowell DUSUP Valve Testing Project 14” Dia - Testing of Globe Valve Dubai
2015 DUSUP / Dutco McConnel Dowell DUSUP Valve Testing Project 14”to 30” Dia - Testing of Ball Valves, Butterfly Valves, Check Valves and Globe Valves Dubai
2015 Saipem Saudi SPN/STAR LTA T&I 3PDM Project  2 x 12” Flexible Lines 1.90/0.7 Pre-commissioning Works Saudi Arabia
2015 Saipem Saudi Aramco – LTA Project 1 x 16”
2 x 12”
Various lengths Nitrogen Purging Works Saudi Arabia
2015 EXTERRAN – Bellargi Energy Dana Gas Project Zora Gas Plant - Nitrogen Leak Testing in Zora Gas Plant Sharjah
2015 Gates Engineering Equipment Rental - - Rental of pumping equipment spread Dubai
2015 Al Wasimi Holdings / Saudi Aramco/ Shaibah Interconnecting Pipelines 36” 36.00 Cleaning, Gauging, Hydrotesting, Dewatering, Drying, Nitrogen Purging, Caliper Pigging and Intelligent Pigging Saudi Arabia
2015 Al Wasimi Holdings / Saudi Aramco/ Shaibah Interconnecting Pipelines 2 X 44” 23.60 & 22.60 Cleaning, Gauging, Hydrotesting, Dewatering, Drying, Nitrogen Purging, Caliper Pigging and Intelligent Pigging Saudi Arabia
2015 Vopak Horizon / NDT Global UT Inspection 2 x 16”   Support Services for UT Inspection Survey Fujairah
2015 NPCC / ZADCO Chemical Cleaning of Inconel Pipes and Flare Tip Surface - - Chemical Cleaning Abu Dhabi
2015 VTTI / Audex Fujairah  LL FZE VTTI Crude Tank Terminal Project 48 / 68 m Dia
x
28 m Height
- Cleaning of Crude Tank Fujairah
2015 Dutco McConnel Dowell / Dana Gas Dana Gas Offshore Pipeline Project 12” 3.1 Cleaning, Gauging, Hydrotesting, Dewatering, Swabbing, Drying and Nitrogen Purging Sharjah
2015 Dutco McConnel Dowell / Dana Gas Dana Gas Offshore Pipeline Project 12” 3.1 Caliper Pigging Works Sharjah
2015 Dubai Petroleum CC-GG Pipeline Project 8” 3.20 Flooding, Cleaning/Gauging, Hydrotesting, Dewatering, Passivation and Nitrogen Purging Dubai
2015 Forequest - - - Equipmental Rental Dubai
2015 Saipem SPA Aribiyah and Hasbah Offshore and Onshore Facilities Project 1 x 4”
2 x 10”
13 x 12”
71.68
70.95/73.77
1.36 to 5.93
Nitrogen Purging Works Saudi Arabia
2015 Contracting and Trading Company (CAT) Saadiyat Island – District Cooling Piping Network 8” to 42” 24 High Velocity Flushing, Hydrotesting, Chemical Cleaning & Chemical Treatment Abu Dhabi
2015 Al Nasr Contracting Company Takreer Project - - Supply of dryer unit + operator on rental basis Abu Dhabi
2015 Petrofac ADCO Asab - - Supply of diesel pumping unit + operator
First & Second campaign completed
Abu Dhabi
2015 Al Nasr Contracting Company / Gasco 10” Pipeline Partial Replacement Project 10” 6.3 De-commissioning, Pre-commissioning and Commissioning Works Abu Dhabi
2015 Dubai Petroleum IP Project - - Supply of launcher and receiver on rental basis Dubai
2015 Rosen – Total ABK Assistance for Inspection Pigging Works 16” 4 Pigging Works Abu Dhabi
2015 Lin Scan Equipment Rental for Inline Inspection Pigging at Gasco Asab - - Rental of pumping spread and manpower for inline inspection pigging Abu Dhabi
2015 ONGC/Bumi Armada Cluster 7 FPSO Project 12”/10”/6” 1/1/1 Free Flooding, Pre-Testing, Post Intallation Leak Testing of Flexible Hoses for FPSO India
2015 Momin Oil Industry 8” Pipeline Pre-commissioning Works 8” 0.45 Dewatering, Swabbing and Drying Jabel Ali, Dubai
2015 Dubai Petroleum Cleaning Pigging Campaign 2015 3 x 18”
1 x 14”
1 to 3 km Cleaning Pigging of various pipelines Dubai
2015 Saipem SPA Saudi Aramco Wasit Project - 16 pipelines Nitrogen Services for Dewatering & Inert Gas lay up for pipelines Saudi Arabia
2015 Overseas AST Company LLC Design & Build Contract Development and Operating of Fuel System at Station in (DHA-AV-02) Dhafrah Air Base Camp No. (136601) Fuel Piping System Network of various diameters
4” to 16”
9.652 Air Blowling, Pneumatic Testing and Air Drying Abu Dhabi
2015 NDT Global/ ADCO Assisting in UT inspection survey 16” 10.00 Assisting in UT inspection survey and drying works Abu Dhabi
2015 Kerzner International, Dubai Atlantis Hotel Sea Water Intake Pipe GPS Mapping Works 42” Sea Intake Pipe 0.90 GPS Mapping Works Dubai
2015 Visen Polymers FZC / Quality International Company Limited Investors Pipeline to Deep Water Berth AT Hamriyah Port 1 x 8” / 1 x 10” / 2 x 12” 1.30 Km each Cleaning, Gauging, Hydrotesting, Dewatering & Drying Works Hamriyah Port in Sharjah.
2015 Calligan International, Dubai Equipment Rental - - Rental of centrifugal pumps Dubai
2015 Stats Group, Dubai Equipment Rental - - Rental of pumps and manpower Abu Dhabi
2015 Technip - Dubai Petroleum Jalilah B Pipeline Project 10” 7.70 Dewatering & Nitrogen Purging Dubai
2015 Lin Scan ADCO NEB Project - - Supply of Break Tanks on Rental Basis Abu Dhabi
2015 G.S Engineering Takreer IRP II Project - - Equipment Rental Abu Dhabi
2015 Technip Total ABK Project - - Supply of chemicals and Pigs Abu Dhabi
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2014-15 Dubai Petroleum/Technip Flooding, Cleaning, Gauging, Hydro-testing, De-watering with nitrogen 30” / 18” /12”
(10 Pipelines
34 Flooding, Cleaning, Gauging, Hydro-testing, De-watering with nitrogen Dubai
2014 Takreer/GS Constructions/Essar Overseas Construction Limited Cleaning & Gauging, Hydrotesting, Dewatering and Drying. 28” 2 x 95 Cleaning & Gauging, Hydrotesting, Dewatering and Drying. Ruwais
2014 Essar Overseas Construction/GASCO 16” Condensate Pipeline Replacement Project - - Hire of Equipments Abu Dhabi
2014 NDT / ADCO Assisting in intelligent pigging survey     Assisting in intelligent pigging survey Habshan/
Bab
2014 Galfar Engineering / ADCO Construction of Flowlines & Well Head Installation at Buhasa 4”, 6” & 8” Various Lengths Cleaning & Gauging, Hydrotesting and Dewatering Buhasa
2014 Matrix Constructions EPC for Batch-1 Plant Modification Project 4” 0.266 & 0.220 Cleaning & Gauging, Hydrotesting, Dewatering, Drying and Nitrogen Purging Works Buhasa
2014 Dubai Petroleum FA-FB 8” Gas Pipeline Repair Project 8” 7.60 Dewatering, Chemical Batching and Nitrogen Purging Dubai
2014 Dubai Petroleum FA-FB 8” Gas Pipeline Repair Project 8” 7.60 Dewatering and Nitrogen Purging Dubai
2014 Dubai Petroleum FA-FB 16” Pipeline Shutdown Project 16” 7.60 De-cruding, Dewatering and Nitrogen Purging Dubai
2014 PTSC/ Swiber Offshore Construction Su Tu Nau Development Project 6”/10”/12”/14”/18” – 7 P/Lines 6-12 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering Vietnam
2014 Pertamina Hulu Energy / PT Rajawali Swiber EPCI GG New Field Development 12” 35 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Drying, Nitrogen Purging Indonesia
2014 Premier Oil Indonesia / PT Rajawali Swiber Chakrawala Naga Pelikan Project 14”/12” 20/32 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Drying, Nitrogen Purging Indonesia
2014 PCML
( Petronas) / Hyundai Heavy Industries
Yetagun Development Project 10” 10 Flooding, Cleaning, Gauging, Hydro-testing, Intelligent Pigging, De-watering, Swabbing, Drying, Nitrogen Purging Myanmar
2014 South Oil Company (SOC) / Leighton Offshore Crude Oil Export Facilities Project 48”
(5 Pipelines)
65 Flood, Clean, Gauge, Hydro test, Leak Testing, Dewatering and Commissioning with Crude Iraq
2014 Saudi Aramco / McDermott Arabia Company Limited/
J.RayMcdermott
Maintain Potential Facilities Project 12” 5.3 Leak Testing and Wetlayup of Flexible pipeline Saudi Arabia
2014 Hitachi Power Pacific Power Station, Singapore 8” 0.5 Cleaning & Gauging Singapore
2014 Oil and Natural Gas Corporation (ONGC) / Punj Lloyd Limited WO-16 & SB-14  Pipeline Project & Buckle detection Project 14”/12”/8”
( 6 Pipelines)
67 /32 / 22 Flooding, Cleaning, Gauging, Hydro-testing & Buckle detection of pipelines of 12” x 11 Kms (WO-5 to WO-15). India
2014 Conoco Phillips/Swiber South Belut Project 12” / 8” 1 / 0.5 Spool Testings Indonesia
2014 Oil and Natural Gas Corporation (ONGC) / Leighton Offshore Pipeline Replacement Project (PRP-3) 14”/12”/10”
( 4 Pipelines)
56 Flooding, Cleaning, Gauging & Hydro-testing India
2014 Gujarat State Petroleum Corporation Ltd.
(GSPC) / Punj Lloyd Limited
Deen Dayal Field Development Pipeline Project & Slug Catcher project 20” dia & 10” dia Pipelines 25 & 17 Flooding, Cleaning, Gauging, Hydro-testing, Intelligent Pigging, De-watering, Swabbing, Drying, Nitrogen Purging India
2014 British Gas India Ltd. / Essar Offshore Subsea Ltd Hydrotesting & Leak testing for BG Panna New SPM Project 12”   Flooding, Cleaning, Gauging & Hydrotesting India
2014 Cairn Energy India Ltd / UGL Engineering Pvt. Ltd. Pre-commissioning of SPM at Bhogat     SPM hydrotesting India
2014 Brunei Shell Petroleum / Swiber Offshore Pipeline Replacement Project 2 16” / 12” / 8”
(12 Pipelines)
29.5 Flooding, Cleaning, Gauging, Hydro-testing,  Leak Testing Brunei
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2013/14 Galfar Engineering / ADCO Bab Gas Surface Facilities Modification and Remedial Works 6” >7.3, 10.0, 8.3, 2.5 & 5.1 Cleaning Pigging and Hydrotesting >Habshan
2013 Dubai Petroleum Pipeline Replacement 12’’,18’’,30’’ 34 Flooding, Cleaning, Gauging, Hydrotesting >Dubai
2013 GASCO / Larsen and Toubro Habshan- Ruwais –Sweihat Pipeline Project 52” / 48” 137 Supply of equipment and Manpower for pipeline Pre commissioning >Abu Dhabi
2013 GASCO / Alsa Engineering and Construction Mirfa -Ruwais Nitrogen Pipeline Project 16” 75 Supply of equipment and Manpower for pipeline Pre commissioning Abu Dhabi
2013 Total Abu Al Bukhoosh / Rosen Intelligent Pigging Project Contract No:4800000158 30”/ 20” / 16”
10” /8” / 6”
(15 Pipelines)
159 Support services for Intelligent Pigging of Pipelines >Abu Dhabi
2013 Vopak Horizon Terminals Limited / Cylingas LLC VHFL Tank Farm Project 39m dia
(9 Tanks)
- Hydrotesting of Crude and Product Storage Tanks Fujairah
2013 South oil Company (SOC) Crude oil Export Facilities 5X48’’ 65 Flood, Clean, Gauge, Hydro test, Leak Testing, Dewatering and Commissioning with Crude Iraq
2013 Saudi Aramco / McDermott Arabia Company Limited/
J.RayMcdermott
Maintain Potential Facilities 16’’/20’’ 5.3 Flooding, Cleaning, Gauging, Hydrotesting, Baseline Survey, wet layup Saudi Arabia
2013 Total E&P Indonesia/Swiber Sisi Nubi Project 16”/16”/20” 5.5/8/3.5 Flooding of subsea pipelines Indonesia
2013 Oil and Natural Gas Corporation (ONGC) / Swiber Offshore Construction Pte. Ltd Cluster 7 Pipeline Project 16” / 14” /12” 10” /8” /6” / 4”
(21 Pipelines)
211 Flooding, Cleaning, Gauging & Hydro-testing India
2013 Conoco Phillips / Swiber Offshore South Belut Project 14”/ 8” 32/5 FCG, post tie in Leak Test, Dewatering, Gel Pigging, Dewatering with Nitrogen Indonesia
2013 Mangalore Refinery and Petrochemicals Limited (MRPL) / Leighton Offshore MRPL Refinery Project 48” 17.4 Flooding, Cleaning, Gauging, Hydrotest, Leak Testing of SPM India
2013 Petronet LNG Limited / TOYO Pigging works for 32”LNG & 10:NG Line at PLDSJ Project for Petronet LNG Project 32”/10” 7.5 Cleaning India
2013 Mangalore Refinery and Petrochemicals Limited (MRPL) / GOL Offshore Ltd Rectification work for Gasket replacement Project 48”   Leak testing of SPM India
2013 Reliance Ltd. Pigging & Rope pulling project 6” 35 Pigging & Rope Pulling India
2013 ONGC Mangalore Petrochemicals Ltd. (OMPL) Cleaning of pipelines by pigging method 14”/10”/8”/6” 6/6/14/13 Cleaning India
2013 Bharat Petroleum Corporation Ltd. (BPCL) Hydrotesting of Dock Pipelines 24” 12 Flooding, cleaning, gauging & Hydrotesting India
2013 Petro Vietnam PTSC / Hyundai Heavy Industries Thang Long Dang DU Project 12” / 10” / 8” / 6”
(15 Pipelines)
19 FCG, Hydrotest, Post Tie in Leak Test Vietnam
2013 Mubadala Petroleum / Swiber Offshore Pearl Oil Ruby Pipeline 14” 315 FCG, Hydrotest, Caliper Pigging, Dewatering, Vacuum Drying, Nitrogen packing Indonesia
2013 Brunei Shell Petroleum / Swiber Offshore Champion Water Flood 16” / 12” / 8”
(12 Pipelines)
29.5 Flooding, Cleaning, Gauging, Hydro-testing,  Leak Testing Brunei
2013 Brunei Shell Petroleum / Swiber Offshore Osprey Field Development Project 10”/16” 9/18 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering, Drying and N2 Purging Brunei
2013 Santos/PT rajawali Swiber Santos Puelong Project 10” 11 Flooding, Cleaning & Gauging, Hydrotesting, Dewatering, Drying, N2 Purging Indonesia
2013 Oil and Natural Gas Corporation(ONGC) / Subsea 7 GS-1 GS-15  Deep sea Project 10” / 8”
(3 Pipelines)
55 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Glycol Swabbing, Baseline Survey, Nitrogen Purging Kakinada , India
2013 Brunei Shell Petroleum (BSP) / Swiber Offshore Bulan-Bulan, Osprey Project 12”/16” 6/6 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering, Drying and N2 Purging Brunei
2013 Premier Oil/Swiber Naga & pelicon 14’’/12’’ 19 / 32 Flooding Indonesia
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2012 EMCO/GASCO Replacement of 16” and 10” Gas Pipeline 16”& 10” 5.2 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering & Drying, Nitrogen Packing Bab Field, Abu Dhabi
2012 ADCO / Galfar Engineering and Contracting Emirates LLC Segregation of units 6 & 7 and D Flow lines (CONTRACT No. 15166.01 / EC 10780) 8”
(9 Pipelines)
3.92 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Swabbing, Drying, Nitrogen Purging Abu Dhabi
2012 GASCO / Union Gas Company Jindal Steel Plant  Pipeline Project 8” 1.5 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Swabbing, Drying, Nitrogen Purging Abu Dhabi
2012 ENOC Lubricants and Grease Manufacturing / Cylingas LLC ELOMP Tank Farm Project 15/7.5/5.3 m dia
(7 Tanks)
  Fresh Water cleaning and blasting of Product Storage Tanks Fujairah
2012 Brunei Shell/Swiber PRP - Decommissioning Project 4”/8”/10”/12”
12 Pipelines
1 to 16 Cleaning, De-Oiling & Decommissioning of Pipelines Brunei
2012 Govt. of Tanzania / Leighton Offshore Tanzania SPM Project 28” / 24”
(2 Pipelines)
14.9 Flooding, Cleaning, Gauging, Hydrotest, Leak Testing of SPM Systems Tanzania
2012 ADCO / Galfar Emirates Bab Gas Surface Facilities 6’’,8’’,10’’ 32 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering & Drying, Nitrogen Packing Abu Dhabi
2012 Brunei Shell/ Swiber Danuu- Babut Subsea Development 12”/12” 22/1 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering & Drying, Nitrogen Packing Offshore, Brunei
2012 Alliance LNG/
Petronas / Stone House/ Maser Offshore
Alliance LNG Re-Gasification Project 30” 4 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering and Drying Malaysia
2012 Indian Oil Corporation (IOCL) / Hyundai Heavy Industries IOCL Paradip SPM Project 48”
(5 Pipelines)
69 km Flooding, Cleaning, Gauging, Hydrotesting, Leak Testing, Caliper EGP Survey ,Leak Testing of SPM Systems India
2012 Saudi Aramco / McDermott Arabia Company Limited/ J.Ray.McDermott Safaniya Field Dev Project (Phase-1) 16”
(6 Pipelines)
35 km De-cruding, Flooding, Cleaning, Gauging , Hydrotesting  and Wet Layup Saudi Arabia
2012 ConocoPhillips / Kreuz Subsea/ PT RajawaliSwiberCakrawala Bawal Field Development Project 14” 40km Dewatering & Nitrogen Packing Indonesia
2012 British Gas Exploration & Production India Limited / Punj Lloyd Limited Panna SBM Project 12” 3 Flooding, Cleaning, Gauging & Hydro-testing, Leak Testing of SPM System India
2012 Oil and Natural Gas Corporation (ONGC) / Swiber Offshore Construction Pte. Ltd D1 Pipeline Project 16” / 14” / 12” / 4”
(4 Pipelines)
18 Flooding, Cleaning, Gauging & Hydro-testing India
2012 Oil and Natural Gas Corporation (ONGC) / Swiber Offshore Construction Pte. Ltd B-193 Subsea Pipeline Project 16” / 12” / 10”/ 8” /2”
(14 Pipelines)
214.3 Flooding, Cleaning, Gauging & Hydro-testing India
2012 Oil and Natural Gas Corporation (ONGC) / Valentine Maritime Ltd / Valentine Maritime Mauritius Ltd B Series & N 15 & N16 Pipeline Project 16”/ 14”/
10” /8”
(4 Pipelines)
51.35 De-watering Drying & N2 Purging of Subsea Pipelines India
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2011 SANTOS/
Swiber Offshore
Wortel Field Development Project 10” 10.4 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Swabbing, Drying, Nitrogen Purging Madura Straits, Indonesia
2011 Dubai Petroleum / Technip (Abu Dhabi) Jalilah Field Development Project 12” / 6”
(2 Pipelines)
54 Flooding, Cleaning, Gauging, Hydro-testing, De-watering with nitrogen Dubai
2011 Brunei Shell/
Swiber Offshore
Champion Flood Project 8' 1.1 Cleaning and Hydrotesting of internally HDPE lined WI Pipeline Offshore, Brunei
2011 ONGC/
Swiber Offshore
ICP-R Project 28”/4” 1/1 Flooding, Cleaning, Gauging and Hydrotesting India
2011 ONGC/
Leighton Contractors
GS-1 GS-15  Deep sea Project 10” / 8”
(3 Pipelines)
55 Flooding, Cleaning, Gauging, Caliper survey and Hydro testing Kakinada , India
2011 ONGC/
Swiber Offshore
North Tapti Gas Field Development Project 18” / 12”
(2 Pipelines)
17.5 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Swabbing, Drying, Nitrogen Purging India
2011 GAIL/
Fernas Constructions
Dahej –Viajypur (Phase-II) Pipeline Project 48”
(3 Sections)
290 Bulk Dewatering, Swabbing, Drying, Caliper survey and Vacuum Drying India
2011 ONGC/
Leighton Contractors
Pipeline Replacement Project (Phase-III) 14”/ 12”/
10” /6”
(12 Pipelines)
79.8 Flooding, Cleaning, Gauging & Hydro-testing India
2011 ONGC/
Swiber Offshore
Mumbai High North Re-Development Project 6", 8", 10" 12", 14" (total 14 segments 90 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering India
2011 British Gas/
Swiber Offshore
BG PL Project 14"/4” 14/14 Flooding, Cleaning, Gauging, Hydrotesting, Dewatering & Drying and Nitrogen Packing Panna Field, West Coast, India
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2010 Abu Dhabi Gas Industries (GASCO) / AL Fannar Contracting Gas Supply Pipeline 24” 2.7 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Swabbing, Drying, Nitrogen Purging Abu Dhabi
2010 ADCO / Al Hussam General Contracting Co. Bab Fields Replacement Pipeline 6”/8’
( 6 Pipelines)
30 Flooding, Cleaning, Gauging, Hydro-testing, De-watering, Swabbing, Drying, Nitrogen Purging Abu Dhabi
2010 Ceylon Petroleum / Leighton Contractors Pvt Ltd Muthurajawela Tank Farm Project 16” 9.1 Flooding, Cleaning, Gauging, Caliper Pigging and Hydro-testing Sri Lanka
2010 Hindustan Petroleum Corporation (HPCL) / Leighton Offshore Vizag Refinery Project 48” 5.5 Flooding, Cleaning, Gauging, Hydrotest, Leak Testing of SPM Systems India
Year Client / Contractor Project Title Dia
(Inches)
Length
(km)
Scope of Work Location
2009 Saudi Aramco / McDermott Arabia Company Limited/ J.Ray.McDermott Long Term Agreement Project 16”
(5 Pipelines)
30 km Flooding, Cleaning, Gauging , Hydrotesting  and Wet Layup Saudi Arabia
2009 Oil and Natural Gas Corporation (ONGC) / Leighton Offshore Contractors Pvt. Ltd Pipeline Replacement Project (Phase-2) 24”/16”/ 12” / 8” / 6”
(17 Pipelines)
58.4 Flooding, Cleaning, Gauging & Hydro-testing Bombay High, India
2009 Oil and Natural Gas Corporation (ONGC) / Global Industries Pvt. Ltd Pipeline Replacement Project (Phase-1) 18”/16”/ 12” 
(6 Pipelines)
54.2 Flooding, Cleaning, Gauging & Hydro-testing Bombay High, India
2009 Oil and Natural Gas Corporation (ONGC) / Punj Lloyd Limited Heera Redevelopment Project 16”/14”/ 12”/10”/8” 
(11 Pipelines)
69.1 Flooding, Cleaning, Gauging & Hydro-testing Heera Field, India
2009 British Gas Exploration & Production India Limited / Swiber offshore Constructions Pvt Ltd BG Hydra Pipeline Project 14”/12”/
4”/1.25”
(6 Pipelines)
52.7 Flooding, Cleaning, Gauging & Hydro-testing, High speed Flushing ,Dewatering, Drying and Nitrogen Packing Tapti Field, India